NOTE: If you do not have a default e-mail program installed on your computer ex: Microsoft Outlook, you can simply copy and paste this email address [email protected] into your browser e-mail such as Hotmail, Yahoo, Freemail, or Google. [Mention of specific web-based email services is not a recommendation or endorsement of those services by the State of Tennessee, but are given as examples only.]


The following outline describes the contents of a Facilities Plan/planning document, using a suggested outline for the presentation of the required information. Some of the information requested may not be applicable for certain projects.

1. SUMMARY, CONCLUSIONS, AND RECOMMENDATIONS
1.1 Statement of the Problem
1.2 Summary of the Alternative Solutions Considered
1.3 Recommended Solution

2. PURPOSE AND NEED
2.1 Study Purpose
2.2 Need for the Project

3. GENERAL INFORMATION
3.1 Existing Facilities and Geographic Area/Population Served
3.2 Optimum Performance Available with the Existing Facilities/Operational Problems
3.3 Existing Collection System (indicate collectors, pumping stations, force mains, and WWTPs)
3.4 Potential for Serving Additional Areas

4. INFILTRATION AND INFLOW
  4.1 Analysis of Infiltration and Inflow
4.2 Steps Being Taken to Reduce Excessive Infiltration and Inflow

5. FUTURE CONDITIONS
5.1 Planning Period (20 years)
5.2 Land Use Projections
5.3 Population Forecast

6. DEVELOPMENT OF ALTERNATIVES
6.1 Minimum of Three Alternatives in Addition to the "No Action" Alternative Compared For Cost- effectiveness, Environmental Impacts, and Feasibility
6.2 "No Action" Alternative
6.3 Chosen Alternative

7. SELECTED PLAN DESCRIPTION
7.1 Detailed Description of Chosen Alternative
7.2 Public Involvement/Public Meeting

8. PROJECT COSTS
8.1 Estimated Construction Costs and Overall Project Costs
8.2 Proposed Financing
8.3 Projected Operating Costs and User Charge Structure

9. ENVIRONMENTAL IMPACTS
9.1 Planning Area and Project Area (indicated on USGS quad map) and a Brief Project Description
9.2 Project Specific Impacts

Maps and Figures

APPENDICES (supporting documentation as appropriate)

 


For more information please call 615-532-0445 or visit the